June 1, 2008
The new Outdoor Aquatic Center is a big hit! Check it out!
Mission Accomplished!
After months of hard work, the new Outdoor Aquatic Center is ready for it's debut!
May 14, 2008
Plastering is complete and the final details are being done to prepare for our grand opening in just 10 days! Lighting is being installed in the pool and the remaining water will be added by tomorrow. Construction of the spray park has begun, looks like fun!
May 5, 2008
Our pool construction crew is busy at work to meet our May 24 deadline. Today they are pouring the concrete pool deck. Electricity is scheduled to be connected Thursday and the fence will be installed next week.
April 3, 2008
The siding and roof of the pool house are almost complete. Work continues on the kiddie pool and tile work begins on the family pool. Work continues at a steady pace and just over seven weeks remain to our target opening date!
March 26, 2008
The bath house is steadily progressing and the pad for the spray park is scheduled to be poured late next week.
March 21, 2008
Workers start plastering the walls of the pool and work continues on the pool house.
March 20, 2008
The bath house frame goes up.
March 18, 2008
The concrete has set; work continues.
March 13, 2008
Workers pour concrete for the floor of the family and children's pools.
March 2008
Construction is underway!
|